Air Force, Boeing agree to new KC-46 schedule, compensation package

By Courtney Albon / March 8, 2017 at 11:17 AM
The Air Force and Boeing have agreed on a new acquisition program baseline schedule for the KC-46 tanker that moves the start of initial operational test and evaluation from May 2016 to November 2017 and pushes a full-rate production decision back more than two years from June 2017 to August 2019. Separately, the two parties also agreed to a compensation package meant to make up for the schedule delay. Air Force spokesman Daryl Mayer told Inside Defense March 8...