Strike Zone

By Jason Sherman / November 8, 2010 at 5:52 PM

Lockheed Martin, prime contractor for the Joint Strike Fighter, says “aircraft component reliability” continues to hamper test flights of the F-35B, the short take-off and vertical landing variant, while the other two JSF variants -- the conventional take-off and landing and aircraft carrier variants -- are tracking “ahead” of the 2010 flight test plan.

The F-35 flight test team completed 52 flight tests in October, two more than planned for the month, the company said in a Nov. 4 statement, which also notes:

The CTOL aircraft logged 22 flights against a plan of 17; STOVL jets flew 27 times against a plan of 28; and the CV jet flew three times against a plan of five.  Additionally, the STOVL jet flew supersonically, and at Mach 1.3 has flown faster than any other variant to date, and achieved 7 g’s, the highest load condition to date and maximum design g’s for the STOVL.

The conventional take-off and landing variant, the lowest risk of the three JSF types intended for the Air Force, is 66 flights ahead of the plan while the aircraft carrier variant is three flights ahead, according to the company statement.

The F-35B, meanwhile, was 41 test flights behind schedule at the end of last month.

F-35 program officials are pursuing a multi-faceted approach to improve tempo, including working to obtain higher levels of spare parts from suppliers to keep the aircraft in a flight-ready condition, while completing the analysis and corrective action planning to address the root cause of any issues.

The November goal is a total of 51 flights, according to Lockheed, with an eye toward 394 test flights through December.