The Navy's Ship to Shore Connector program must be rebaselined because of a test and training craft delivery schedule breach, according to a selected acquisition report obtained by Inside Defense . The Ship to Shore Connector's production schedule faces two major risks: the propeller and the gearbox. On Feb. 3, a program deviation report memorandum was signed to notify the milestone decision authority, the document states. The SAR was sent to Congress on June 21 . Propeller manufacturer General Electric...