Five Missile Defense Agency programs run the risk of incurring delays and inefficiencies because their schedules do not meet best practices, the Government Accountability Office says in a new report. "These results are significant because a reliable schedule is one key factor that indicates a program is likely to achieve its planned outcomes," the GAO report, addressed to MDA Director Lt. Gen. Patrick O'Reilly, states. "Our analysis suggests that estimated time frames and costs of these programs are either not...